Street Slurry Seal & Stripping (update #3)

September 18, 2024: Update on the timeframe for the 2nd week of street slurry work (this is what Brandywine has notified me):

Trash day WILL NOT change next week, it will remain the same day (Monday, September 23, 2024).

Work/construction will ONLY be on Tuesday of next week (September 24, 2024), refer to attached image.

Also, depending on how construction goes today, Brandywine may not need tomorrow (Thursday, September 19, 2024) to complete their work. But, this is a BIG maybe! If they can complete enough today, it might not require that they return tomorrow (for Phase 1).

Thank you.